Software Project Management MCQs

Topic-wise practice questions for Software Engineering. Test your knowledge, check solutions on demand, and pace your preparation.

Zero-leak answer engine • Rate-limited explanations
Practice in Timed Mode
Q11medium
(Code/Console Logic) A developer checks the project status via a command-line tool. Based on the output, which task is currently the Bottleneck?
Q12hard
A software project has 5 external inputs, 2 external outputs, and 3 internal logical files. All are of "Average" complexity. If the weighing factor for Input is 4, Output is 5, and Logical File is 10, what is the Unadjusted Function Point (UFP) count?
Q13medium
A client keeps requesting "just one more small button" or "just a slight change in color" every week without extending the deadline or budget. This phenomenon is known as:
Q14easy
What is the difference between Reactive and Proactive risk management?
Q15medium
You are using the Basic COCOMO model where Effort (E) = 2.4 * (KLOC)^1.05. If your project is estimated at 10,000 lines of code (10 KLOC), what is the estimated effort in Person-Months (rounded)?